Large-volume Chatham-Kent developments need a separate water-demand review. Allow at least four weeks for modelling, and do not assume the system can supply the requested flow.
Key information
Large-volume Chatham-Kent developments need a separate water-demand review. Allow at least four weeks for modelling, and do not assume the system can supply the requested flow.
On this page
Who needs the review
The PUC names greenhouse, agricultural, industrial and large commercial developments as examples of large-volume users. Complete the Application for Large Water Users so staff can assess pressure, capacity and effects on neighbouring customers.
This review is separate from a routine residential meter fee. A proposed demand is not an approved entitlement; the distribution system may need a lower rate or may be unable to provide the requested capacity.
Sources: Official Chatham-Kent large-water-user applications and flow limits information
Analysis and the maximum flow
The minimum review time is four weeks from submission for hydraulic modelling. Additional field investigation can extend it. Incomplete applications are not processed, so the clock should not be treated as a guaranteed approval deadline for a partial submission.
The PUC determines the allowed maximum in litres per second. The applicant must install a rate-of-flow control-valve system set to that maximum and monitored by the PUC. Staff may reduce the requested demand where supply or capacity is insufficient.
Sources: Official Chatham-Kent large-water-user applications and flow limits information
Submission and agreement
Submit to ckamfm@chatham-kent.ca or fax 519-352-3432. Mail applications to Chatham-Kent PUC, AM/FM Department, 325 Grand Avenue East, PO Box 1191, Chatham ON N7M 5L8.
An approved or reduced request requires a formal agreement with PUC. Ask the AM/FM Department at 519-360-1998 about a proposal before committing equipment to an assumed supply rate. Do not start connection work based on an unreviewed application.
Sources: Official Chatham-Kent large-water-user applications and flow limits information
Quick reference
| Item | Details |
|---|---|
| Example developments | Greenhouse, agricultural, industrial, large commercial |
| Minimum modelling period | Four weeks |
| Possible extension | Additional field investigation |
| Approved unit | Litres per second |
| Required control | Rate-of-flow valve set to approved maximum |
| Application email | ckamfm@chatham-kent.ca |
Sources: Official Chatham-Kent large-water-user applications and flow limits information
Steps to follow
- Describe demand
Complete the large-user application with the development’s requirements.
- Await assessment
Allow modelling and any field work.
- Agree and control
Sign the approved agreement and install monitored flow control.
Sources: Official Chatham-Kent large-water-user applications and flow limits information
Questions and answers
Which developments are examples of large-volume users?
Greenhouses, agricultural, industrial and large commercial projects.
Source: Official Chatham-Kent large-water-user applications and flow limits information
What does the review assess?
Pressure, capacity and effects on adjacent water customers.
Source: Official Chatham-Kent large-water-user applications and flow limits information
What is the minimum modelling period?
Four weeks from submission.
Source: Official Chatham-Kent large-water-user applications and flow limits information
Can field investigation make it longer?
Yes.
Source: Official Chatham-Kent large-water-user applications and flow limits information
Are incomplete applications processed?
No.
Source: Official Chatham-Kent large-water-user applications and flow limits information
Is the requested demand guaranteed?
No. Some systems cannot provide it.
Source: Official Chatham-Kent large-water-user applications and flow limits information
What unit is used for the approved maximum?
Litres per second.
Source: Official Chatham-Kent large-water-user applications and flow limits information
What equipment must limit the flow?
A rate-of-flow control-valve system set to the approved maximum.
Source: Official Chatham-Kent large-water-user applications and flow limits information
Is an agreement required after approval?
Yes. A formal agreement with PUC is required.
Source: Official Chatham-Kent large-water-user applications and flow limits information
Where can I email the application?
ckamfm@chatham-kent.ca.